Question # 6 Updated:2017-07-19

Near the end of a Sprint, the team realizes that they will not be able to complete the stories they had committed to.
What is the best course of action for the team?

A. Add resources and team members to meet the goals of the current Sprint.
B. Ask the Product Owner to decide which stories can be delayed until the next Sprint.
C. Decide on a new definition of 'done' for the Sprint Backlog Items.

1.Select Download EX0-008 VCE & PDF Exam Questions & Answers Without Cost (100% FREE):
AOOWE is dedicated to provide real and updated EX0-008 exam questions and answers, FREE of cost,Free Download.

2.All EX0-008 Exam Questions Include Detailed Answers with Explanations:
Exam databases include the latest questions and answers from the EX0-008 Dumps. On each exam page you will find a date located at the top of the page indicating the most recent update to the list of test questions and answers.

3.User Friendly & Easily Accessible on Mobile Devices:
AOOWE is extremely user friendly.Users can quickly get to the EX0-008 Questions & Answer dumps, which is free of ads or distracting information. The site is mobile friendly to allow testers the ability to study anywhere, as long as you have internet connection or a data plan on your mobile device.

Thanks Dump4exam technical&financial support for EX0-008 Dumps!
Pass Your EX0-008 Exam Easily On The 1st Try With Our Free practice exam questions and answers!