If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

A. Senior User
B. Executive
C. Corporate/programme management
D. Senior Supplier

Answer Clike
Which is a purpose of the Risk theme?

A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
B. Establish a cost-effective procedure to identify, assess and control uncertainty
C. Establish mechanisms to control any unacceptable deviations from plan
D. Establish mechanisms to manage risks at the corporate or programme level of an organization

Answer Clike
Which is part of the PRINCE2 definition of a project?

A. An undertaking that consists of at least two management stages
B. A description of what must be delivered in order to gain acceptance
C. The total of a plan's products
D. A temporary organization that is created for the purpose of delivering business products

Answer Clike
Which is a type of issue?

A. A lesson
B. A request for change
C. An Exception Report
D. A risk with an estimated high impact

Answer Clike
Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,

A. benefits, progress, risk,
B. benefits, quality, risk,
C. change, quality, progress,
D. benefits, customers, quality,

Answer Clike
Which task is performed by the Change Authority?

A. Set a change budget
B. Approve or reject a request for change within approved limits
C. Refer changes that exceed budgetary limits to the Project Manager for approval
D. Update the configuration management system when a change is approved

Answer Clike
Which process provides the Project Board with the information it requires in order to commit resources to the project?

A. Managing Product Delivery
B. Initiating a Project
C. Controlling a Stage
D. Directing a Project

Answer Clike
Which should be funded by a change budget?

A. Increase in agreed scope
B. Initiation stage
C. Change Authority
D. Handover activities

Answer Clike
Which of the following describes a use of a Configuration Item Record?

A. Define the identification scheme to be applied to the project
B. Identify the techniques and procedures required within the Work Package
C. Record the change in a product's status
D. Record the reporting requirements for the Work Package

Answer Clike
Which characteristic distinguishes a project from regular business operations?

A. Produces benefits
B. Introduces business change
C. Manages stakeholders
D. Incurs cost

Answer Clike
What process aims to ensure accurate progress information is provided to the Project Manager?

A. Starting up a Project
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project

Answer Clike
Where should an off-specification be recorded?

A. Risk Register
B. Issue Register
C. Work Package
D. Configuration Management Strategy

Answer Clike
Which is a benefit of using PRINCE2?

A. Provides a defined structure of accountability, delegation, authority and communication
B. Includes techniques for critical path analysis and earned value analysis
C. Enables a Project Manager to be accountable for the success of a project
D. Prevents any changes once the scope of a project has been agreed

Answer Clike
Which statement is FALSE?

A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
B. A project's output is any of the project's specialist products
C. A project benefit is only realized after the project has closed
D. A project outcome is the result of the change derived from using the project's outputs

Answer Clike
Which is a responsibility of the managing level within the project management team?

A. Set project tolerances
B. Approve stage completion
C. Ensure that the products are produced within the constraints agreed with the Project Board
D. Appoint the project management team

Answer Clike
Which is a purpose of quality planning?

A. Define the structure of the project management team
B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
C. Document approval records for those project products that have met their quality criteria
D. Produce the Project Plan with resource and schedule information

Answer Clike
Which product identifies the management stages and timescales of a project?

A. Project Brief
B. Project Product Description
C. Project Plan
D. Initiation Stage Plan

Answer Clike
How should the Team Manager report that tolerances are forecast to be exceeded?

A. Create an Exception Report
B. Create a Highlight Report
C. Raise an issue
D. Grant a concession

Answer Clike
Which is a purpose of a Project Product Description?

A. Records the costs and timescales for delivery of the project's final product
B. Shows the dependencies between the project's products to aid planning
C. Provides a list of all the products to be delivered by the project
D. Defines what the project must deliver in order to gain acceptance

Answer Clike
Which is a purpose of a Product Description?

A. Provide the cost tolerance available for individual products
B. Define reporting frequency
C. Record the quality checks completed for the End Stage Report
D. Document the level of quality required of a product

Answer Clike
Which is a purpose of the Business Case theme?

A. Identify which role is responsible for producing the Business Case
B. Identify the project's outputs
C. Establish the controls to manage changes that may impact the project benefits
D. Establish a viable investment proposition

Answer Clike
Who is the key project decision-maker in the project management team?

A. Corporate management
B. Executive
C. Change Authority
D. Project Manager

Answer Clike
Which is a purpose of a Project Brief?

A. Capture lessons from previous projects
B. Ensure that there is a common understanding of the starting point for the project
C. Confirm that the Project Plan is able to deliver the Business Case
D. Define the quality techniques and standards to be applied during the project

Answer Clike
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Pay for the project
D. Specify the benefits of the project

Answer Clike
Which describes risk impact?

A. Timeframe within which the risk might occur
B. The trigger that occurred giving rise to the risk
C. The effect of the risk on the delivery of project objectives
D. How likely the risk is to occur in a given project situation

Answer Clike
Which is a purpose of the Controlling a Stage process?

A. Produce a Team Plan for the work to be assigned to a Team Manager
B. Select and implement actions that will resolve deviations from a plan within tolerance
C. Obtain approvals for products delivered in a Work Package
D. Update a Project Plan to incorporate the actuals from a Stage Plan

Answer Clike
Which statement about stages is true?

A. Management stages should be of the same duration
B. The use of technical stages is mandatory
C. The use of management stages is mandatory
D. Management stages are driven by specialist teams

Answer Clike
Who should act as the communication channel between a project and corporate or programme management?

A. Project Board
B. Project Assurance
C. Project Manager
D. Project Support

Answer Clike
Who represents the three project interests on a project?

A. Project Manager
B. Project Support
C. External project stakeholders
D. Project Board

Answer Clike
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

A. Checkpoint Report
B. End Stage Report
C. End Project Report
D. Product Status Account

Answer Clike
Which is a purpose of a Project Product Description?

A. Form part of the Work Package for the project product
B. Provide the initial project budget to be refined in the Business Case
C. Document the project mandate and gain approval for the project from the Project Board
D. Define the quality required of the project's product

Answer Clike
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery

Answer Clike
Which statement about the Directing a Project process is FALSE?

A. Supports the PRINCE2 principle of manage by exception
B. Is triggered by a request to initiate a project
C. Covers the day-to-day activities of the Project Manager
D. Provides a mechanism for the Project Board to assure that there is continued business justification

Answer Clike
Which is a purpose of the Plans theme?

A. Identify, assess and control any potential changes to the baseline
B. Establish the project's structure of accountability
C. Assess and control uncertainty
D. Understand whether the targets are achievable

Answer Clike
Which of the following is NOT an event-driven control?

A. Project mandate
B. Checkpoint Report
C. Exception Report
D. End of a stage

Answer Clike
Which is a responsibility of a risk owner?

A. Identify risks to the project that might occur in their department
B. Own and authorize the use of the risk budget to fund risk responses
C. Manage, monitor and control all aspects of an assigned risk
D. Determine project risk appetite

Answer Clike
Which is a type of issue?

A. An expected dis-benefit
B. An off-specification
C. A project outcome
D. A scope tolerance

Answer Clike
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

A. minimum necessary is done to decide if a project is worthwhile
B. aim is to establish sound foundations to achieve a successful project
C. Project Brief is assembled and approved
D. project approach appropriate for delivering a project is selected

Answer Clike
Which of the following is NOT a purpose of the Closing a Project process?

A. Plan the activities required to close a project
B. Enable a comparison of the original objectives of a project against what was actually achieved
C. Enable premature closure if the Project Board request that a project should no longer continue
D. Provide a fixed point at which acceptance for the project product is confirmed

Answer Clike
Which is NOT a purpose of the Organization theme?

A. Define a project management team structure
B. Define the level of tolerance for each level of the project management team
C. Define the Project Board's responsibility for directing the project
D. Define which role is accountable for the project's success

Answer Clike
Which two roles are linked by the Managing Product Delivery process?

A. Corporate or programme management and Project Board
B. Project Board and Project Manager
C. Project Manager and Team Manager
D. Team Manager and external supplier

Answer Clike
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

A. Directing a Project
B. Managing a Stage Boundary
C. Controlling a Stage
D. Starting up a Project

Answer Clike
Where should a Team Manager look for information on the quality required for a product?

A. Project Initiation Documentation
B. Product Description
C. Team Plan
D. Quality Management Strategy

Answer Clike
Which is a difference between management and technical stages?

A. Management stages require planning and technical stages do not
B. Technical stages can overlap and management stages cannot
C. Management stages deliver products and technical stages do not
D. Technical stages require resources and management stages do not

Answer Clike
Which describes the 'Identify Risks' step within the recommended risk management procedure?

A. Identify responses to risks documented in the Business Case
B. Gather information about the project environment and objectives
C. Identify the roles to be involved in risk management activities
D. Identify uncertainties that may impact on the delivery of the project objectives

Answer Clike
Which principle helps to define what should be included and what should be excluded from a project?

A. Defined roles and responsibilities
B. Focus on products
C. Manage by stages
D. Continued business justification

Answer Clike
Which of the following is the Business Case used for during the Managing a Stage Boundary process?

A. Enable the Project Board to decide whether or not to authorize the project
B. Justify the continuing viability of the project
C. Enable the Project Board to decide whether or not to authorize project closure
D. Justify the initiation of a project

Answer Clike
Which statement defines a risk?

A. A certain event occurring in the future that will have a negative impact on the project's objectives
B. An event that has already occurred that the Project Manager must deal with immediately
C. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
D. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

Answer Clike
Which describes the 'Implement' step within the recommended risk management procedure?

A. Project Support will allocate the risk budget to fund the selected risk responses
B. The risk owner will decide the best response to control the risk
C. The risk owner and the risk actionee will carry out activities to control and deal with the risk
D. The Project Manager will formulate the Risk Management Strategy

Answer Clike
Which regular report provides the Project Board with a summary of stage status?

A. Communication Management Strategy
B. Project Brief
C. Highlight Report
D. Checkpoint Report

Answer Clike
Which statement describes the Implement' step within the recommended risk management procedure?

A. Take planned action to respond to a risk
B. Implement the responsibilities for risks defined in the Risk Management Strategy
C. Assess the proximity of a risk
D. Identify the level of risks that can be tolerated by the project

Answer Clike
Upon what environment is PRINCE2 based?

A. Operational
B. Configuration
C. Programme
D. Customer/supplier

Answer Clike
What process is used by the Project Board to respond to an Exception Report?

A. Controlling a Stage
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project

Answer Clike
When are tolerances for a Work Package agreed?

A. When accepting a Work Package
B. As work on each product within the Work Package begins
C. Once ail products have been developed and approved
D. When the Stage Plan is authorized by the Project Board

Answer Clike
Which risk response type is appropriate to respond to an opportunity?

A. Accept
B. Fallback
C. Exploit
D. Transfer

Answer Clike
Which is an objective of the Managing Product Delivery process?

A. Sign-off completed Work Packages
B. Ensure the Business Case is kept under review
C. Report progress to the Project Board
D. Ensure that work on products is authorized and agreed with the team

Answer Clike
Which product is NOT created in the Managing a Stage Boundary process?

A. Benefits Review Plan
B. End Stage Report
C. Lessons Report
D. Exception Plan

Answer Clike
Which is NOT an objective of the Controlling a Stage process?

A. Implement actions to control the impact of risks that occur during the stage
B. Review the Business Case at regular intervals to assess the impact of changes that occur during the stage
C. Update the Business Case with any changes agreed with the Project Board
D. Coordinate the delivery of products as agreed in the Stage Plan

Answer Clike
What product defines the reporting requirements between the Project Manager and Team Manager?

A. Project Brief
B. Product Description
C. Team Plan
D. Work Package

Answer Clike
Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

A. Defined roles and responsibilities
B. Learn from experience
C. Manage by exception
D. Focus on products

Answer Clike
Which is a purpose of the Risk theme?

A. Establish a method for the implementation of continuous improvement during the project
B. Identify, assess and control problems that have occurred
C. Provide the Project Board with a time-driven control to capture all project risks
D. Establish a cost-effective procedure to identify, assess and control risks

Answer Clike
Which is a purpose of an Exception Plan?

A. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
C. Identify the actions required to recover from the effect of a tolerance deviation
D. Define the changes which are within the scope of the change budget

Answer Clike
Which is a true statement about management stages and technical stages?

A. Technical stages can overlap but management stages CANNOT
B. Management stages are the responsibility of the Project Manager, technical stages are NOT
C. Technical stages create products, management stages do NOT
D. Management stages require quality control, technical stages do NOT

Answer Clike
Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,

A. producing an achievable Project Plan
B. preventing poorly-conceived projects from ever being initiated
C. obtaining approval from all stakeholders
D. setting up the required project controls

Answer Clike
Which role is responsible for specifying the project benefits?

A. Corporate or programme management
B. Executive
C. Senior User(s)
D. Project Manager

Answer Clike
Which is a purpose of a Project Brief?

A. Enable the assembly of the project mandate
B. Describe the reporting requirements of the various layers of management involved with the project
C. Describe how changes to products will be controlled
D. Provide a solid basis for the initiation of the project

Answer Clike
Who carries out audits that are independent of the project?

A. Quality assurance
B. Project Assurance
C. Project Support
D. Project Manager

Answer Clike
Which is a typical core activity within configuration management?

A. Assessment
B. Communication
C. Quality control
D. Status accounting

Answer Clike
Which is an objective of the Directing a Project process?

A. Review and approve a project mandate
B. Ensure corporate or programme management has an interface to the project
C. Define how risks, issues and changes will be managed
D. Obtain approval for completed products

Answer Clike
Which is NOT undertaken during the Initiating a Project process?

A. Review why the project is needed
B. Identify if the project is sufficiently aligned with corporate objectives
C. Show how the outcome is to be achieved
D. Appoint an Executive and Project Manager

Answer Clike